Final Shipment of Uranium Arrives at Ishwardi's Rooppur on Foggy Morning

Ishwardi, Pabna, Rajshahi

S

S M Raja, Ishwardi (Pabna), Upazila Correspondent

S M Raja, Ishwardi (Pabna), Upazila Correspondent • 27 Nov • 2 min read • 2 views · 2 impressions

Updated 27 Nov 2026

Final Shipment of Uranium Arrives at Ishwardi's Rooppur on Foggy Morning
Final Shipment of Uranium Arrives at Ishwardi's Rooppur on Foggy Morning

The ninth and final shipment of nuclear fuel brought from Russia for Rooppur, the country's first nuclear power plant, has reached the project site. On Friday (November 27) at 5:48 AM on a foggy morning, three specialized lorries carrying uranium entered the project area under the supervision of the army and strict security from other law enforcement agencies. With this, the process of bringing nuclear fuel in nine scheduled shipments for the two units of the Rooppur Nuclear Power Plant has been completed.

According to project-related information, these uranium shipments were brought in two consignments of additional fuel for the first unit and seven consignments for the second unit. Under the plan of Russia's state atomic energy corporation Rosatom, 163 uranium assemblies were scheduled to be brought on seven cargo flights for the second unit, along with 48 more assemblies on two cargo flights for refueling the first unit. The arrival of the final shipment marks the completion of that plan.

Built with Russian technology, the Rooppur Nuclear Power Plant features two VVER-1200 model units. Each unit has a generation capacity of 1,200 megawatts. Once both units are fully operational, the plant will be able to supply a total of 2,400 megawatts of electricity to the national grid.

Meanwhile, alongside the completion of fuel imports, test power supply from the plant's first unit is also progressing. On November 23 at 10:20 AM, electricity supply to the national grid resumed for the second time. At this stage, testing is scheduled to supply 300 to 350 megawatts of power for 10 to 24 hours.

Read nextWomen's Mini Marathon Held in Sherpur

Earlier, on November 17 at 3:16 PM, the first unit connected to the national grid for the first time. After generating electricity continuously for more than eight and a half hours, production was temporarily halted at 11:50 PM. That test generated a peak of 375 megawatts of power.

Project Director Dr. Md. Kabir Hossain said that the second phase of experimental power supply began on November 23 at 10:20 AM. During this stage, testing will continue to supply 300 to 350 megawatts of electricity to the national grid for 10 to 24 hours.

According to the contract with the Russian contractor, after 10 months of trial operation, commercial power supply will begin gradually at full capacity from the first unit. At that time, the Bangladesh Atomic Energy Commission will take over responsibility for the first unit from the Russian contractor through provisional takeover. Later, Nuclear Power Plant Company Bangladesh Limited (NPCBL) will begin operations as the operating organization through a government gazette notification.

Through lengthy construction, fuel imports, and ongoing technical testing, the Rooppur Nuclear Power Plant is now moving toward full generation. Once both units are operational, it is expected to boost the country's power generation capacity while playing a vital role in ensuring energy security.

— Daily Best News Desk • Fearless in the search for truth

Reported by S M Raja, Ishwardi (Pabna), Upazila Correspondent • Edited by the Daily Best News desk. Send corrections to [email protected].